Update on the Golf Courses
The Golf Course Maintenance team addressed the following this week:
- Verti-cutting and amendments application to The Pines greens
- Wetting agent application to selective dry areas on The Pines fairways and tees
- Mowing of rough on The Pines
- Raking of The Pines bunker face rough to break up algae
- Renovation of The Pines large practice putting and chipping green which involved verti-cut, aeration 8mm hollow tines and top-dressing
- The Members’ Working Group assisted with the clean-up of green waste and mulching on The Palms 11th hole
The Palms golf course renovations:
- Greens mown at 4mm
- 2nd top-dressing of greens
- Tees, green aprons and fairways mown
- Bunkers cleaned out and detailed
- Commenced topdressing tees, green aprons and fairways
- Irrigation head trim
Next week, the team plans to:
- Apply amendments and lightly dust The Pines greens
- Apply pre-emergent herbicide to The Pines tees, green aprons and fairways
- Trim detail The Pines bunkers
- Dust The Palms greens
- Complete top-dressing of The Palms tees, green aprons and fairways
- Mow The Palms rough
- Apply 2nd top-dress to The Pines large practice putting green
- Aerate and top dress the northern driving range tee
Staff removing cores pines on the large practice putting green
|
Verti-cutting The Pines 18th green
|
Second applications of greens topdressing
|
Second mow on the fairways at 14mm
|
Bunker detail
|
Topdressing tee complexes
|
Topdressing green aprons and surrounds
|
|